New two-month ‘dumsor’ timetable for Accra released

Residents of Accra will experience another phase of from October 5 to December 5, 2021 according to a document sighted by Starrfm.com.gh.

Parts of Accra to experience ‘dumsor’ for two months

According to the document, this will allow the Ghana Grid Company Limited (GRIDCo) to undertake “planned works” within the Achimota – Accra Central Lines

Some of the areas to be affected have been categorised into groups A, B and C.

Group A – Adabraka Old Timers, Mamprobi, Chorkor, Ageege, Lartebiokorshie, Valco Trust, Teachers Hall, among others.

Group B – Appolo Theatre, Asylum Down, Adabraka Market, Korle Gonno, Sukura, Mamprobi PolyClinic, JamesTown, Mataheko etc.

Group C – includes Central Police Station, Cocobod, Kingsway, Abossey Okai, Chorkor, Appiah Danquah, Graphic Press House, SSNIT among others.

See full document below;

October 5 to December 5 ‘dumsor’ timetable

October 5 to December 5 ‘dumsor’ timetable

Source: Pulse.com.gh